dear experts
while transfering bom to CJ20n following error is coming
All assignments are already current
Message no. CN152
please help me
regards
etr
closed
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
delete all the compenent assignment in the network activities along with reference points and Run MRP on the project using MD51.
Next reassign the reference points and tranfer the BOM using CN33.
Note: Make sure the assignment of that BOM is not available for network activities.
Rgds
Sudhir Reddy
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
thanks for your reply but i am working on 5.0 this note is not applicable please any other solutions.
regards
etr
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Not sure which release you are working on.
But Please check the Note: [160270|https://websmp130.sap-ag.de/sap(bD1lbiZjPTAwMQ==)/bc/bsp/spn/sapnotes/index2.htm?numm=160270].
Hope it helps...
Thanks!!!
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
9 | |
9 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.