We have budgetory control over material & services for the project .
While posting the resrevation for the material , system checks the available budget & give error is no margin is available .
But while posting the serviecs via service entries , system does not check the available magin & posts the entrie amount eventhough the Availble budget turns negative.
Pl guide on the issue .
Hi,
Due to technical reasons Budget availability check is not triggered during G.R or Service Entry (ML81N).
Please apply following notes to resolve it
Reason for No availability = Note 46209.
Solution = Note 696362.
Thanks
Saikishore.Ganga
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
Go to SPRO --- Investment management - Project as investment measures--Planning and budgeting ---Define tolerance limits for availbility control
Select your availbility control profile and change the tolerance group to ++
Thanks
S.Murali
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
95 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.