Transfer operative project to simulation version & vice versa?

Former Member
0 Kudos

Hi All

Please someone explain me step by step process, and prerequisites to copy or transfer operative projects to simulation version & vice versa.

Thanks in advance

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

answered

Former Member
0 Kudos

HI

For Operative Projects we can create Simulation Versions t.code CJV1

We can compare different Project Versions with Operative Project (S_ALR_87013539 / 38).

For Simulation version to Operative project use t.code CJV4