on 07-23-2009 7:37 AM
Hi,
Iam new to PS.One of the requirement is we need a report for the projects with details of Planned hours and Actual hours.Suggest me is there is any STD report.
Regards
A.Sureshbabu.
Hi
Use SAP1 t.code to find out the standard reports in your system.
Thanks
S.Murali
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
You can use report CN41N. Please select a layout and add in the required columns in that report.
Regards,
Kabir