How to send Network and Activity for Project?

Former Member
0 Kudos

Hi Experts,

We have to send all the Project information outside SAP. We found the message type PROJECT01 which can be used but it sends the Project information till the WBS (Work Breakdown Structure) level. The Network and Activity information is missing in PROJECT01. Is there a standard message type which can be used?

Regards,

-Jitendra

Accepted Solutions (1)

Accepted Solutions (1)

varshal_kachole3
Active Contributor
0 Kudos

Hi:

Use Following BAPIs

1) BAPI_PROJECTDEF_GETINFO

2) BAPI_PROJECT_GETINFO

3) BAPI_NETWORK_GETINFO

Hope it helps...

Thanks!!