Mat requirement grouping is not happening at Level 1 WBS.
Following setting are maintained
1.Autmomatic Req Grp is set at Proj Def
2. Level 1 WBS is made as grp WBS
3. Periodic lot size is maintained for the Mat as MB
What else is missing?
answered
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
Have you using the MRP groups ?
if yes
Go to SPRO----Material - Procurement--Activate MRP group for Requirements grouping
Enter the Plant and MRP group and check the Grouping check box.
Thanks
S.Murali