We installed fresh system IDES ECC 6.0 with SQL SERVER 2005 on Win 2003 32 bit , but its too slow. Their HIT RATIO is between 50% - 70% MAX which has to be more then 95%.

NOTE: AFTER 3-4 HOURS, I AM GETTING "BLUE SCREEN ERROR"

In task manager

PF USAGES: 6-8 GB

ALL THESE ENCLOSED ENTRIES IS INCREASING AFTER EVERY SECOND.

sqlservr.exe

cpu usage- 00 - 02

Memory- 1,229,698k TO 6,321,980k

jlauch.exe

CPU: 00-02

MEMORY: 193,604 & 30,872

disp+work.exe

CPU: 00-02

MEMORY: 67,604K+

Please suggest some ways to tune r server.

Thanks

Rhishabh

Edited by: Sap_basis_admin on Jul 22, 2009 7:21 AM

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

i think this probelm due to hardware.Check if any driver failure see system log.

"BLUE SCREEN ERROR" - many times comes due to RAM not compatable with motherboard .

you can try to change RAM (contact to Hardware vendor)

SurendraJain

Answers (2)

Answers (2)

Former Member
0 Kudos

Done

Former Member
0 Kudos

Please let us know the sp version of windows and also the physical memory available on the system.

Regards,

Pavan

Former Member
0 Kudos

SP3 is the windows version and this system configured as a virtual server & RAM is 2 GB.

Former Member
0 Kudos

To be frank you need more physical memory on the system, since its a ABAP + JAVA system and usually JAVA alone takes a lot of memory.

Regards,

Pavan

former_member204746
Active Contributor
0 Kudos

2GB is not enough, you must size your system with http://service.sap.com/quicksizer .. or ask your hardware vendor to do this for you. Most of them do it for free.

For a dual stack system, I would use 4GB at least, and probably more like 8GB.