on 07-21-2009 11:03 PM
Hi Guys
During creating an assembly order, availability check comes up with missing parts.
Can someone tell me how to proceed from here? I checked the material master fro the missing part and in MRP2, procrement type = x.
What are my options, can i save this order even though i have missing parts? How do i carry on?
Thanks
Ahmad Yahya
Hi,
relevant material master setting is in MRP3, availability check. If you would like to skip the check, set the indicator to KP - no check.
Best regards,
Zuzana