on 07-21-2009 6:40 AM
Hi,
Some items are lying in the project stock. When I create the reservation from the Network activity (from Project builder), system takes the movement type as 281 but not the Spl. stock indicator. How to create the reservation for the Project stock? I mean, I need the reservation with movement type as 281 and Spl. stock indicator Q assigned to it. Is it possible directly from CJ20N ?
thanks in advance
Vinodh
Pl check seetings for the procurement indicator assigned to the network in transaction OPS8. Change the priority for project to 1.