on 07-20-2009 2:54 PM
Hi Team
During change in BOM using ECM, I am allowed to change it with same ECN. If we change it with diff. ECN, it keeps the history of previous ECN.
Foe example a BOM has 3 diff. items, which is created with ECN: 001.
Now if we delete 2 items & add 1 item, then system displays all the items with respective change no.
i.e. Total 6 line items are displayed.
Pls suggest solution.
Thanks
Hi Bhushan,
For your case you need to :
Create a different Change Number through T Code: CC01 and create a new BOM (for the same material as it exists without ECN agaist any components) with this new change number. If you now delete / add some components (after you enter the BOM with this new ECN) ;it will be exclusively be recorded with this ECN.
If you use the same ECN; and do further changes at the components; all chages till date will be recorded as you have mentioned.
Thanks,
Ravi.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
103 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.