I have maintained network scheduling tpye as backwards in OPU6 and also maintained as "backwards" in control parameters for WBS scheduling. This is meant for both template project and operative project/network profiles.
I have created a template project with WBS heirarchy along with network activity scheduling types set as backwards.
Now while "including" the template project in an operative project, the system copies all the WBS elements and network activities from template project. However, the network schedulihng type is coming as FORWARDS, instead of "backwards".
Can anyone suggest what could be the problem here??
Best Regards
Srikrishna
Hi
Check this SAP notes
Note 1327079 - CJ20N: Scheduling type with copying II
This notes applicable upto ECC 6.0, so check this and apply
Thanks
S.Murali
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
your cust. is correct.
activating check box for template profile data while copying the project hopes will resolve the issue.
if the check box is active it copies the data from profile or else it copies data from the project which you copy.
rgds
Anish
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
Please note that I am trying to include a WBS element from a template project. One would right click operative WBS element and choose include and the system prompts to include WBS element either from Operative WBS or Standard WBS.
I am not trying to use the copy function in CJ20N intial screen.
Any other ideas?
Regards
Srikrishna
User | Count |
---|---|
89 | |
7 | |
6 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.