Hello Gurus,
I am working on DRP(Distribution Resource Planning). My problem is,
I need to add some days to the current date and get the resulatant date in factory calender.
Ex: Current date - 07/20/2009
Days: 8
Resultant date = current Date + Days
= 07/30/2009 (This is excluding week ends).
Basically date needs to be calculated w.r.t factory calender(excluding week ends and holidays defined in factory calender).
Could someone let me know how to acheive this?
Thanks in advance!!!!
Use this function module.
BKK_ADD_WORKINGDAY