Can Budget be activated in only one WBS????

regards,

SAP PS

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

HI,

An Alternative could be to use user status, if the no of WBs are less you can deactivate Availability control using user status and only the required /WBS will have Availability control.

Regards

Vinayak.

Answers (2)

Answers (2)

Former Member
0 Kudos

hi,

I guess as per the wbs hirarchy the value flows wrt the ticks in budget profile i.e. total or annual or bottum up etc.

IF you do not give tick to total or annual and then give budget check to only one WBS then checking for only WBS might work

but activation will be at project level. Exactly what is objective to be achieved?

Regards,

Sameer

Former Member
0 Kudos

Hi

You can release the budegt for only one WBSE. but budget control is Project level.