Material replication

Former Member
0 Kudos

HI,

when i am replicating material from R3 to EBP.matetrial is not replicating.

when i execute the r3as it is showing me in warning that object is in waiting status

in r3am1 only DNL_CUST_ PRD0 is in status done and rest are in red status.

against MATERIAL the status is wait and right corner it has given some information that Parent is not OK: DNL_CUST_PRD1

kindly suggest what needs to be done.

regards

subbu

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

Hello,

Pl.check the mentioned category is available in table T027 in R/3.

If it doesn't exist in R/3, an initial load doesn't bring up the

category. In such case first maintain the material group in R/3

by transaction OMSF. Afterwards please do the initial Load for the

object DNL_CUST_PROD1. Afterwards it is possible to download materials

assigned to that category.

regards,

Gaurav

PLEASE GIVE FULL POINTS FOR USEFUL REPLIES

laurent_burtaire
Active Contributor
0 Kudos

Hello Ubbu,

In addition to what wrote Ramarao, check your customizing with blog below:

[How to replicate material master from R/3 to SRM|https://www.sdn.sap.com/irj/scn/weblogs?blog=/pub/wlg/5728] [original link is broken] [original link is broken] [original link is broken];

Regards.

Laurent.

Former Member
0 Kudos

Hi

If the technical settings and connections from SRM to R/3 is properly defined and after replication you can

Check the inbound and outbound queues in R/3 and SRM . You can check the transaction code SMQ1 & SMQ2 for inbound and outbound queues.

If the queues processed succesfully , you can check the desired material code in COMMPR01 transaction code in SRM.

regards

Narahari

-