on 07-16-2009 11:46 AM
Hi All,
I am creating a Sub order withing a follow up action in which the sub order has to be created and the status of the superior order has to be set to 'Technically completed'. Now the issue I am facing is :
1) Sub order cannot be created after the status of superior order has been changed to 'Technically Completed'.
2) If I try to change the status of Superior order after the sub order has been created, I am getting an error that "Open sub-orders still exist", Are there any other dependencies for this?
How can I perform both the steps in teh same FM?
Thanks,
Vasuki
Hi
1) Sub order cannot be created after the status of superior order has been changed to 'Technically Completed'.
In followup action Use a FM to create a Sub order first ....then use different FM to close/complete the order technically.
2) If I try to change the status of Superior order after the sub order has been created, I am getting an error that "Open sub-orders still exist", Are there any other dependencies for this?
In customization of followup action select Indicator: function module called after posting
But with the same FM i am not very sure how it is possible.
Regards
Sujit
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
89 | |
7 | |
6 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.