Good morning,

I am planning a product in a sim version in APO, if I do a regen planning run it works but if I run the same scenario (and reset the results) with a net change it is not included (not planned) in the planning run.

Am I missing something obvious??

Thanks in advance.

Former Member
Former Member replied

Hi UKuser,

1) It may happen that the product view and background job will have two different

heuristics selected, please check

2) Check the job log and application logs during the time of job run.

3) In background job, if you select entire planning horizon, then it will plan. In

product view, it works based on SNP horizon

4) Before u retry, delete the existing planned orders and retry

Regards