hi guys,
my customer is using base planning object to build his project plan cost.
at first , we planned our cost in CJ40 using bpo . Overhead calculation is done automatically.
in a second time, rate is changing. he runs cj46 but overhaed cost are not recalculated.
my customer must go to each wbs of all the projects and modify it manually to update overhead cost.
do you know how to avoid this situation ?
thks for your help
LLB
HI,
CJN1 - Individual Processing (Revaluation at Actual Prices)
Run this transaction when ever there is a change in the Activity price.
this is manditory otherwise costs won't be recalculated.
Rgds
Sudhir reddy
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
This message was moderated.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
Use CJ47 t.code and make sure version, period and fiscal year entries are correct.
In CJ47 create variant and assign all the WBSE and execute.
Thanks
S.Murali
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.