planned overhead cost re-calculation after rate modification

Former Member
0 Kudos

hi guys,

my customer is using base planning object to build his project plan cost.

at first , we planned our cost in CJ40 using bpo . Overhead calculation is done automatically.

in a second time, rate is changing. he runs cj46 but overhaed cost are not recalculated.

my customer must go to each wbs of all the projects and modify it manually to update overhead cost.

do you know how to avoid this situation ?

thks for your help

LLB

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

HI,

CJN1 - Individual Processing (Revaluation at Actual Prices)

Run this transaction when ever there is a change in the Activity price.

this is manditory otherwise costs won't be recalculated.

Rgds

Sudhir reddy

Former Member
0 Kudos

hi,

thanks for your suggestion but non recaalculation occurs !

regards

luc

Former Member
0 Kudos

This message was moderated.

Former Member
0 Kudos

hi,

thnaks for your suggestion but no recalculation occurs!

regards

Former Member
0 Kudos

Hi

Use CJ47 t.code and make sure version, period and fiscal year entries are correct.

In CJ47 create variant and assign all the WBSE and execute.

Thanks

S.Murali

Former Member
0 Kudos

hi,

thnks for your suggestion but no recalculation occurs !

regards

luc