cancel
Showing results for 
Search instead for 
Did you mean: 

Multiple Assignment of Investment Measures

salim_shakir3
Explorer
0 Kudos

I have configured the investment program type so that its is not relevant for Budget distribution and have unchecked single assignment. I attached a project with multiple assignments to 2 position ids as 80:20. Yet when I see all my actual reports with 0000000005 profile the WBS with multiple assignments do not get rolled up to the program position based on the set ratio. it gets rolled up with 100% value to any one position.

Is any thing wrong?

sms

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

View the reports in IM module and not PS. I don't think changing DB in PS is going to help.

Regards

Sreenivas