WIP STOCK

Former Member
0 Kudos

Hello frinds,

my clint wants to know the WIP stock ,Plant wise ,Date wise and material number wise ,Operation wise

i know there is no standard report ,Pls guide me , if i have to write a query which tables i have to join & in what sequense

Please Pour some light on it

Regards,

Girish

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Dear Girish,

i think u can get it from MB53

just check & revert back

Regards

kumar

Former Member
0 Kudos

Hello kumar,

in my plant there are 126702 material and i want it operation wise in what stage my input is

tks for u r eairly replay ,Pls suggest me

Regards

girish

Former Member
0 Kudos

go to COOIS...

Select components in the list..

exclude the system status DLV and TECO( the orders without the status DLV and TECO are those in WIP)

Execute..

you will get all the componets that are in WIP..

YOu can sort the material column in the ascending order and total the quantity field...

karthick

and for operation wise list also you can select confirmations in the list or operations in the list of COOIS

Former Member
0 Kudos

Hi Karthick

what about the quantity which is Partilly deliverd ,and in my senerio we are dooing operation wise confirmation

it also cant show me at what operation lvel my stock is

Pls explain u r view,i have already try that my clint dont want that

Regards

Girish

Former Member
0 Kudos

For Invidual processing

KKAX is for determining the WIP and KKAY is for Display of the WIP.

For Collective Processing,

KKAO for Determining the WIP and KKAQ for the display of WIP.

Regards

Ratan