How we can update the time profile ?

Former Member
0 Kudos

Hello,

How we can update the time profile daily in PP/DS ?

This time profile we need in the background job scheduling.

Please suggest

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi Sunil,

The Time Profile is first to be maintained by going to the current settings (S_AP9_75000087) and creating one Time Profile as per your requirements.Here you define the Display Period and Planning Periods. If you create Relative days/weeks/ months then it is calculated in relation to the current date.So for example if you want to view 10 weeks in past and 20 weeks in future from today, you give the Start Date as -10 and End date as +20.after selecting Relative month/week/day in the Daye column.

Similar method is used for both the Display Period and Planning Period. Preferably ristrict the Display period.

You also have the option of Absolute time where you enter the start date and the finish date as an absolute value in the set period type.This will hard code the dates for you.

This Profile which you have created needs to be attached to Detailed Scheduling Planning Board - View 1/2/3 which ever you want to use by going to the Profile icon on the top and in the pop up click on the More profiles Tab and putting this value in the Time Profile Box.

Thanks,

Harsh

Answers (1)

Answers (1)

maheshbabu_mg
Advisor
Advisor
0 Kudos

Hello Sunil,

Time profile need not be updated daily, if you have maintained the period in relative terms in the profile settings.

For example, if you have maintained Planning period:

Date Relative month

Start Date -2

End Date +3

Now, every day, the satrt & end date is calculated as current date -2 Months to current date+3 months.

Thanks,

Mahesh