on 07-15-2009 10:37 AM
Dear Experts,
I am looking for Capacity requirement planning in PS using Work center. I am facing a problem in this process.
I have carried out the following steps:
1. Created a work center with category 0006 and maintained the capacity data with category 002. I have maintained the costing data also along with activity type and formula (SAP008)
2. I have created a project and mentioned the work center against 1 activity in the network, the calculation key is 2(calculate work). The project is scheduled and released.
3. When look into the report CM50 / CM53, its giving me a message as below:
No capacity requirements were found in the evaluation period
When I opened the message the details are as follow:
No capacity requirements were found in the evaluation period
Message no. CY140
Diagnosis
No capacity requirements records were found for the selected orders in the evaluation period.
Procedure
You should check the evaluation period in the time profile in Customizing. Try refreshing the chart by clicking on the right mouse button and selecting 'Refresh'.
And when I proceed further into the report by selecting OK for that message I found the report as:
Rem.cap.reqs as 0(Zero) and Avail.capacity (full), where as, as per me the Rem.cap.reqs should show the data with the work center occupancy and the available capacity should be the full capacity of the work center capacity data - the mentioned capacity of the project for that duration.
But it is not showing anything in the report. I am not able to understand why this is showing like this.
I have checked the Overall Profile ID in the network profile it is SAPPS_G020 (PS: Evaluation, standard overview).
Can any one help in sorting this issue?
Thanks in advance,
Regards,
Praveen
Hi
Have you mainatined the standard availabilty capacity in capacity header screen
Double clcik on the capacity catergory in capacity tab
Enter the standard availabilty capacity
Ex:
Start 07:00:00
Finish 18:00:00
Length of breaks 00:00:00
Operating time 11.00
Planning details
Check Relevant for finite schduling
Can be used by serveral operations.
Thankss
S.Murali
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
solved.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Looking into the settings you had done, you must get it.
Pl. check in CM01 for the load (by selecting Standard overview). If you find '0' for the weeks displayed then in the Project you might not have planned.
In the project NWA, pl. check whether you had mentioned the workcenter alongwith No.of persons and the percentage. If you maintain thest things then you must get the same in the requirements.
Regards,
L.Balachandar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Balachandar,
Thanks for your reply.
I have checked the load in CM01 it is still showing no requirements. i.e., the requirements column as 0.
I have cheked the network activities also, I have mentioned the work cneter, Number of person - 2 percentage 100, and clalculation key 2 (calculate work) I have mentioned the time duraion in capacity area of the work center master as 7 hrs, so the work calculated is 14 hrs.
So there is no problem in the requirement planning.
But this is not reflectiong in the reports.
Regards,
Praveen
Hi,
Check the Note: [79179|https://websmp230.sap-ag.de/sap(bD1lbiZjPTAwMQ==)/bc/bsp/spn/sapnotes/index2.htm?numm=79179]
Hope it helps.
thanks!!
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Varshal Kachole,
Thanks for your reply.
I have checked the said note number 79179, the settings in transaction BS42 are available as mentioned in the note.
I have also checked one more note 33099, the function CY_BT_KBED_CREATE is available as per the modification in the note 33099.
But still the error exists.
Regards,
Praveen.
Hi Praveen,
Please cross check the following for Capacity Planning.
Defining Shift Sequences - OP4A
Defining Strategy Profile - OPDB
Defining Overall Profiles - OPDO
Even check Control Capacity Availability - OPSP and Profile parameter in CMPC .
Check which Planning period date type, Start and finish , Calender id and Fiscal Year variant.
Regards'
Syed
Hi Syed,
Thanks for your reply.
1. I don't have shifts, we have only single shift i.e., general shift from 09:00 - 17:00 with a break of 1 hr, so I have mentioned that timing in the capacity header data of work center.
2. I am using overall Profile SAPPS_G020 (PS: Evaluation, standard overview) which is of std. SAP, and the strategy profile used in the overall profile is SAPSFCT005 (Fin.sched.for./disp.acc. to setup group)
I have changed the time profile also, the details I mentioned in my previous thread, please refer to it.
But still not able to get any clue out of it.
Thanks a lot for your reply again.
Regards,
Praveen
hi,
Check the following
1. Work Center details scheduling start time, end time, break time maintained and costing tab activity type and formula mantained.
2. maintain the pricing in KP26.
3. assign the work center in network activity.
4. check the plan/actual cost value
5. check the capacity requirement reports. CM53/CM55.
Hi AP,
Thanks for your reply.
1. Work Center details scheduling start time, end time, break time maintained and costing tab activity type and formula mantained.
2. maintain the pricing in KP26.
3. assign the work center in network activity.
4. check the plan/actual cost value
5. check the capacity requirement reports. CM53/CM55.
1. The work center details are maitained in the capacity header data.
2. Maintained the proce for the activity type in KP26
3.Work center is assigned in the network activity
4. The cost for that work center acording to the activity tyep price is showing correctly in the plan values.
5. When I run the report CM53 / CM55 / CM01/ CM50 its giving me a message
No capacity requirements were found in the evaluation period
And its showing 0 requirements in the report.
Regards,
Praveen
Hi Experts,
Thanks to every one.
I have solved this issue.
The problem was in the workcneter master Capacity tab there is a filed Other Formula in that field we have to mention SAP004 and ensure that the formula is a tick on Work center capacity requirement in transaction OP21.
And also in the Schduling tab of the workcenter master the other formula field needs to be maintained with the same forumla SAP004
This message was moderated.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Saikishore.Ganga,
Thanks for your reply.
I have checked the Time profile also.
The capacity requirement falls under the below dates:
Earliest Start Date: 20.07.2009
Earliest Finish Date: 07.08.2009
Lastest Start Date: 22.09.2009
Lastest Finish Date: 13.10.2009
And the time profile period is as follows:
Data Read Period:
Entry Type: J (Number of calendar months)
Start Date: -12 (01.07.2008)
Finish Date: 6 (31.01.2010)
Evaluation Period:
Entry Type: J (Number of calendar months)
Start Date: -12 (01.07.2008)
Finish Date: 6 (31.01.2010)
Planning Period:
Entry type J (Number of calendar months)
Start date -2 (01.05.2009)
Finish date 6 (31.01.2010)
Dispatching of backlog:
Entry Type G Number of calendar days
BacklogDispDate 0 15.07.2009
In any case the requirement period is within the time profile period.
But still I dont understand why this is giving that message and not showing any requirement data.
Thanks and Regards,
Praveen.
User | Count |
---|---|
103 | |
14 | |
10 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.