Hi,

Iu2019m not able to get person assignment tab for the activity in cj20n.

I have maintained work and workcenter for each activity.

Can any one help me on this, I have checked note 543362 and have maintained the same.

But i dont know what is missing.

Thanks,

Chandru

Accepted Solutions (1)

Accepted Solutions (1)

stheurkar
Active Contributor
0 Kudos
Former Member
0 Kudos

Hi Sandeep,

I have maintained all the steps specified in the discussion but still not able to get the person assignment tab.

Is there any customization missing ?

Thanks,

Chandru

Edited by: Chandru Chandru on Jul 15, 2009 11:34 AM

stheurkar
Active Contributor
0 Kudos

Hi,

goto OPUU (Maintain Network Profile) Transaction...double click on your project related Network Profile.

In Network Parameter subscreen....Cap. reqmts check box must be ticked.

Ensure this.

Regards

Sandeep

Former Member
0 Kudos

Hi

Yes you need to do some settings in SPRO

SPRO-PS-Structures-Oerative structures-Network-User Interface settingsLayout of activity detail screen- Define layout activity detail screen

Select your network profile with TAB01(Labour & Materials) and click details icon

In detail screens on tab page

You have 5 screens in that any one of the screen change to 17 Personnel Assignment to Activity/Element

Thanks

S.Murali

Former Member
0 Kudos

Hi Murali and sandeep,

No still i am not getting it.

Thanks,

Chandru

Former Member
0 Kudos

Hi

Maintain the HRMS data in your work center and try

Ex:

maintain the person in HRMS screen

Thanks

S.Murali

Former Member
0 Kudos

Murali,

Yes it is maintained; i had done this earlier and have also succeeded, but did not face such problem.

when i go to planning board for Capacity planning -> workforce planning i get a error message " No requirements were found for the selection criteria".

Any guesses atleast to solve this.

Thanks,

Chandru

former_member201206
Active Contributor
0 Kudos

Hi Chandru

Actually the note 543362 (written by me) should give you all the information. Anyway double check the following again.

1. Is the flag 'capacity requirement' of network set?

2. Is the scheduling for network done?

3. Is the work for activity maintained?

4. Which work center is maintained for involved activtiy. Call CR03 for this work center.

4.1. In work center, in the capacity tab. Is the formular for field 'Other formular' maintained. Default is SAP008

4.2. Click of button 'HR assignment', is the HR resource assigned?

If all the checkitems do not help, you can open a customer message to let SAP have a look.

Kind rgards

Zhenbo

Former Member
0 Kudos

Sandeep & Murali ,

This is issue is solved, the problem was because of work center formula, I had not maintained SAP008 in others

The response from this forum is really great, good quality answers compared to forums

Keep up the good work guys.

Thanks a lot for the extra effort.

Regards,

Chandru

Former Member
0 Kudos

Thanks Zhenbo, i have solved it. it was because of workcenter formula

Thanks,

Chandru

Edited by: Chandru Chandru on Jul 15, 2009 3:38 PM

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

You must create work center from T-code CNR1---- PS releated Work Center and Use capacity category as 002 (Labour) and work center category 0006 (Project Management). Assign this work center in activity with some work assigned. Then you can see person assignment tab.