on 07-15-2009 8:38 AM
I have some problems with the MS Project import to implement the requirements.
Now I create one Thread for all questions because otherwise I would create many Threads ^^
1. If I assign a resource with a business partner I get the information that the BP isn't known. But if I put the BP in cProjects into the resource there is no problem.
-> for this point I read that there is no customizing necessary. There must be the BP in the field "code".
2. How can I fill for the project definition, phase, checklist, phase the responsible rolle and responsible person?
Hi Denis,
Sorry, cause I bring bad news again... As far as I remember there was no way to import the responsible role from MSProjects to cProjects. Here are some answers I got previously in this issue:
- The Import and Export of Responsible Roles and Responsible Resources is not possible with cProjects 4.0 and 4.5
- It is not possible to use the BAdI for extending the Im-/Export functionality with the Responsible Roles/Resources
- The mapping canu2019t be changed so that a Im-/Export of Responsible Roles/Resources is possible
Kind regards,
Neil
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
11 | |
6 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.