Budget from Cost element Planning

Former Member
0 Kudos

How to copy the cost element planning values as budget?

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

closed

Former Member
0 Kudos

Hi

Use IMCCP3 t.code to copy the cost element planning values as budget.

In processing options if your project budget is alrady has the budget then select the Budget as supplement/return check box. Otherwise system will through the error.

If you are createing the fresh budget for this project then no need to select the check box.

Thanks

S.Murali

Former Member
0 Kudos

Hi,

goto CJ30 select the plan values column, goto menu>edit>select>select all. again goto menu>edit-->copy view.

or use IMCCP3 - Transfer Plan to Project Budget

Rgds