on 07-14-2009 3:24 PM
Hi All,
Can we use Network as Statstical cost object like WBS Elements.
Regards
N.Raju
Thanks murali..
Iam clsoing this.
Regards,
N.Raju
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
I think you cannot use Network as Statstical cost object like WBS Elements, because you can allot the budget only WBS level. for Network order you will not able allot any budegts in STD SAP.
Thanks
S.Murali
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.