on 07-14-2009 1:05 PM
Hi
I would like to know what are the typical reports that are developed in APO using the BI module.
and also typical activities of BI guys during implementation of APO.
Hi AAL123,
Ideally speaking, the function of BI role is not only to develop
reports.
BW is a tool which itself is a reporting tool in which all
data will be pulled and available at anytime in infocubes.
The BW/BI team pulls the data from various sources, construct
suitable infocubes/strucutres etc., and all the data available
in infocube so that any user can simply extract the data
and view/download iit in BW.
The methodology behind BW is to reduce report preparations
and to make all data availble for user.
Regards
R. Senthil Mareeswaran.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
thanks all
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
There are many available reports in APO for different scenario like, for 'optimization' run we can get total 'unfulfilled demand' from the application log of the optimizer run.
We can get reports on 'resource utilization' rate of plants for different time bucket.
Basically BI guys play role in APO implementation after the configuration of different module. So, you can say BI consultant's role starts at the testing phase. However if DP is there in the implementation scope, then you may need BI guys. Specially when you are creating CVCs (DP master data) from BW.
At the time of blue printing customer suggest what kind of reports they want, to analyse the planning results. Those numbers requirements of different reports may exceed later, when actually the customer gets a good idea of the APO process. So, to meet the customer's demand of several kind of reports, BI consultants are required in a APO implementation project.
A BI consultant extract datas from different APO key figures.
Thanks,
Satyajit
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
These are some reports in APO:
SNP and PP/DS:
/SAPAPO/CRES_CAPACITY_LENGTHEN - If you have changed the factory calendar recently then you will have to run this
SAPAPO/SDORDER_DEL, or report - /SAPAPO/SDRQCR21: Delete hanging delivery
SAPAPO/RRPEVAL : Log for Last Planning Run
/SAPAPO/RRPLOG1 : Display Logs
/SAPAPO/OPT11 : Display Log of Optimization Runs
/SAPAPO/CDPS_REPT : Order and Resource Reporting
/SAPAPO/PPL1 : Production List
/SAPAPO/RRP_NETCH : Display Planning File Entries
/SAPAPO/RTO_ORD_COMP :Compare PP/DS Production Data Structures
/SAPAPO/DELETE_PP_ORDER - delete any PP firmed orders attached to the plant.
DP
/SAPAPO/MP41B - Promotion Reports
/SAPAPO/MC8K Manage Job Logs
/SAPAPO/TSCONS : Consistency Check for Time Series Network
/SAPAPO/MC62 Maintain Characteristic Values
Thanks,
Satyajit
Edited by: Satyajit Patra on Jul 14
User | Count |
---|---|
8 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.