Hi ,

I am new to project systems and need to write a report to upload the plan cost for a project/WBS element combination , similar to transaction CJ40.

Now in CJ40 when i enter with a project / WBS Element combination in some case i can see number of years in period drop down and in some cases i see Overall or a single year , since i need to validate the year also , can you please tell me which table will store these years for the project / wbs element.

Regards,

Arun

Accepted Solutions (1)

Accepted Solutions (1)

former_member203098
Active Contributor
0 Kudos

Hi,

Check with the table TBP1C and feed plnning profile as input.

Regards,

Nag.

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi ,

I found a solution to the problem as mentioned by Nag we have to use the table TBP1C , which is the table for the profile .

For the project get the planning profile (PROJ-PPROF) , use this planning profile in table TBPIC with the applicatiion = Project (APPLIK= P) and value type = Plan ( WRTTP = '1'). , This will tell if we can plan overall or anual for the project.

Thanks a lot Nag and Murali for the response.

Regards,

Arun

Former Member
0 Kudos

This message was moderated.