on 07-13-2009 7:30 AM
Hello ,
We have a batch job which calculates the statistical forecast values for all CVC. This batch has 4 variants, ie the CVCs are evenly distributed under all four variants. Now the issue is, only one of the variant completes in GREEN mode & others in RED when the process chain is started.
Surprisingly, when you check the status of these variants in SM37 they are GREEN. So the issue is the jobs finishes RED in RSPC but GREEN in SM37. Can anyone please throw light on this.
Thank you,
Regards
RAHUL CHITTE
Rahul,
I believe that not all the time you are getting these type of issues. I mean previously it was ok with the process chain too. But somehow now you are facing this issue when you try with process chain.
Can you check the job logs in sm37, for the concerned varieant?.. are there any error masseges?
I think you need to run 'LC check for time series master data' (u2018/SAPAPO/TS_LCM_REORGu2019) and 'Cons check for existing time series network' (u2018/SAPAPO/TS_LCM_CONS_CHECKu2019).
I hope this helps...
Thanks,
Satyajit
Edited by: Satyajit Patra on Jul 13
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks Satya for your concern to peeping in this issue.
Nope there is no need of running the programs mentiond by you .. because we have list of jobs which run monthly. They dont have the problems... but only couple of them fail in RSPC, they are fine in SM37 as well as there spool is fine too.