Internal Order Budget Allocation - KO22 T.Code

Former Member
0 Kudos

hi,

Dear friends i am facing a problem while allocating budget for an internal oredr by using a t.code KO22 Overall budget is in gray mode i am unable to assign overall budget it is gray mode

system giving below message

You are maintaining budget values for one or more measures (orders or

WBS elements). The overall budget and/or the annual budget are not

available for input.

There are two possible reasons for this.

o A program type for investment programs is entered in the budget

profile for the measure. This program type is intended to make a

link between the measure and an investment program that has this

program type mandatory. If there is no link to this kind of

investment program, it is also not possible to create any overall

budgets on the measure.

o The measure is already assigned to an investment program position, but this program position is set up to distribute budget values

directly to the measure. In this case, you cannnot create overall

budgets directly. However, it is still possible to distribute budge

values using the budget distribution function in the menu for

investment programs. If budget distribution of annual values is als

set to active in the program definition, then you are also limited

to creating the annual budgets for the measures using the budget

distribution function in the investment program menu.

please how to come out from this problem please guide me

with regards

Prakash

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

I feel in your system, investment management module is activated. If that is the case, the overall budget must have defined for Investment IDs and you can distribute the budge to the different measures under it.