Dear SAP Guru's,

in a process industry production takes place in different stages.

For a particular stage let us say Blending there will be 5 phases where we use different resources.

Instead of creating 5 resources in recipe i wish to go with one resource called blend.

At the same time i need to capture reporting data of resources of individual phases also.

How can this be achieved.

Should i go for secondary resources.

System by default will pick the resource assigned to operation for all the phases under it.

Kindly Give ur inputs