on 07-11-2009 5:20 AM
Dear SAP Guru's,
in a process industry production takes place in different stages.
For a particular stage let us say Blending there will be 5 phases where we use different resources.
Instead of creating 5 resources in recipe i wish to go with one resource called blend.
At the same time i need to capture reporting data of resources of individual phases also.
How can this be achieved.
Should i go for secondary resources.
System by default will pick the resource assigned to operation for all the phases under it.
Kindly Give ur inputs
Thanks & Regards,
Karad D D
for each operation in your routings you can set a "Control key".
check it out.
if you need to customize those keys goto tranz. OP00
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
pls reply to my this query
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
91 | |
7 | |
7 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.