Hi all,

while creating transport request from Charm , i am getting error " The Last Action triggered is locked in task List".

Please help me to unlock this as i am not able to create any TR for development.

Regards

Andrew

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

Hi Andrew,

Execute tcode TMWFLOW/MAINTINST select your maintenance or project cycle. Double click it and select your cts project -> right click and select unlock.

Thanks,

Suman

Former Member
0 Kudos
Former Member
0 Kudos

Hi ,

Go to SCMA open your Task List, select Project releated tasks --> Right click --> lock/unlock subsequent groups

this will unlock all below tasks.

regards

Naveen kumar