Actual overhead calculation

Makal
Active Contributor
0 Kudos

Dear Friends

During project execution, system always checks for the budget availability (Availability control is configured). For material & services, system will check availability on GR/IR quantity & service acceptance. The I'll have to run CJ44 for overhead calculation. I just want to know, is there any way that CJ44 can execute automatically, once you do GR/IR & service acceptance with respect to network activity? Or can we configure it to run periodically (May be twice a day) in the background?

Thanks

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

CJ44 is a period end activity normally, if you want to carry out daily couple of times, then you need to schedule the same in the background.

Use SM36 for executing the same in background.

Rgds

Sudhir Reddy

Makal
Active Contributor
0 Kudos

Thanks for the info Sudhir

How do you schedule CJ44 in SM36? Can you please post the steps?

Thanks

Former Member
0 Kudos

Hi,

goto CJ44>system>status> pick the progrma name>SM36>enter job name>click on step>enter the program name and variant save it and back>click start condition> enter specific dates and save it>click on job selection enter the job name which is already created and execute...

Rgds

Sudhir reddy