on 07-10-2009 9:59 AM
Hi SRM Gurus,
Does SRM have budget availability check for IO?
Or it just capture the config made by r/3?
Thank you!
Regards,
Chrisell
Hi Chrisell,
SRM has budget check functionality as oof standard. However you still need to set the backend configuration for budget and availability control. Based on these controls SRM would do a budget check.Pl check this note for detailed info.
Note 1081758 - FAQ: Budget Check/Display
Note 520717 - Budget check in EBP
Regards,
Sanjeev