Dear Experts

1) how actual and planned costs, actual and planned revenues are captured in project please explain me with example.

2) can we copy material text to cj20n?

Regards

etr

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Nag thanks for your reply,

my second query is if any texts are maitained at materal master level can we copy those texts to cj20n Project builder material componet screen.

you are not cleared my first query . my doubt is when transfer BOM to Projeect those costs are called as Planned and when we issue materials from project those costs actua costs? this is my doubt please elaborate

regards

etr

Former Member
0 Kudos

Hi,

2.When you assign the material code in the Components screen, Material description gets copied from the material master.

1. For your first query, you yourself has given the answer,

a) when you planned the materials, it is planned cost and when you actually consume it , actual costs will flow.

b) Similarly, when manpower (internal) is assigned to the activity, planned costs will come whereas when you do the confirmation of the activities Actual costs will flow.

c) For services, when you create Service entry sheet, actual costs will flow.

Regards,

L.Balachandar

former_member203098
Active Contributor
0 Kudos

Hi,

Advise you to refer the below link for point 1. please elaborate point 2

http://help.sap.com/saphelp_erp60_sp/helpdata/en/86/98853478616434e10000009b38f83b/frameset.htm

Regards,