i have created a scheduling agreement with a material i want to use the material in a contract with another vendor, is there any way i could use the material or i have to terminate the scheduling agreement and create the contract. in case of canceling the agreement what are the steps involved i mean the T Codes.
Hi,
First af all you have not mention that is ther any subsequent delivery documents are exist against that scheduling agreement or not....if yes then you cannot delete the scheduling agreement unless u reverse the deliveryin t-code VL09 and by cancelling billing docs in VF11(if invoice created) as well...
If thr is no Deliveries, then you can delete that scheduling agreemnt very well, by going VA32 enter agreement no., press enter
on top selct sales doc option and delete the agreeement...
Reg
JJ
Edited by: Jagsap on Jul 9, 2009 2:11 PM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Just go for rejection at header level or item level or even u can delete the agreement if nothing has been delivered
vipin
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
107 | |
12 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.