on 07-09-2009 10:09 AM
Hi PS Guru,
I am doing CNS0 against third party order..i m writing step what i do...
if im wrong kindly suggest me
i click on component tab in pup up i fill planned goods move date and ship to party ...then i enter delivery quantity..and then save
then again u go in 1st screen of CNS0.and click on deliver tab.....and select delivery no. in next screen i go in chnage mood and write the picking qunatity and then i click on PGI tab and then save
but in VF01 not showing billing document and i see in MMBE not reducing material quantity...
kindly suggest me...
what are steps delivery to billing..from CNS0
Regards
Akil
self
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Aqueel,
Please refer these two links for your answer :
http://help.sap.com/saphelp_45b/helpdata/en/d7/b8853488601e33e10000009b38f83b/frameset.htm
http://help.sap.com/saphelp_45b/helpdata/en/dd/56078c545a11d1a7020000e829fd11/frameset.htm
Thanks,
Dhruv
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
9 | |
8 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.