How to change the status in CHARM

Former Member
0 Kudos

Hi gurus.

I'm finding a way on how I can change the status of the Change Document (CD) in CHARM from "Authorized for Import" to "Production" without using action "Transported Correction to Prod".

This is because our Basis team have already imported the corrections into production system using the back-end transport process (unix tp) and not using the CHARM action, but I need to synchronise/update the status in CHARM.

Any suggestions?

Thanks,

Tess

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Tess

You need to create a new action and use method call HF_SET_STATUS to set the status to 'Production' E0006. Then you have to define conditions to allow it to appear in worklist.

Ming