on 07-09-2009 6:24 AM
Hello
I have some problems with the MS Project Import.
The help i find is not really exactly.
Who to schedule during a MS Project import.
I mapped the fields for the import so for example the project definition object:
FINISH_DATE PDCP cProjects Project Definition FINISH_DATE_FIX
START_DATE PDCP cProjects Project Definition START_DATE_FIX
My project in MS Project has the start 11.11.2009 and the scheduled end 08.12.2009.
But when I import a project in cProjects I have a start date 09.07.2009, calculated start 09.07.2009 and calculated end 10.07.2009
on every object (task, project definition...) I have the wrong date after import.
what is the problem?
Edited by: Denis Müller on Jul 9, 2009 7:30 AM
Hi
There are two options
Either you go for
1. mapping duration of Task or Phases with acivity duration in MSP and pass only start date,
system will calculate end date
or
2. try by using constraints, CONSTR_TYPE_FIN and CONSTRAINT_TYPE for start and end date,
for this you need Ms project to maintain values
let all know th support pack you are on
Niranjan
Let me know if it helps
Edited by: Niranjan Dandekar on Jul 9, 2009 11:38 AM
Edited by: Niranjan Dandekar on Jul 9, 2009 11:45 AM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
I don't know what information do you need:
cProjects 4.5 SP 6
MS Projects 2003 SP 3
I tested it and get an good result.
Now the fields "earliest start", "earliest finish", "latest start" and latest finish are filled but the field "start date" and "finish date" aren't filled.
I estimated that the fields "start date" and "finish date" are filled.
In MS Project I filled the fields "start" and "finish". So I think this fields should be filled in cProjects.
Is this expectation wrong? why?
Edited by: Denis Müller on Jul 14, 2009 12:35 PM
Hi Denis,
If I am not wrong, the fields start and end date don't exist in cProjects, but earliest start/ finish and latest start /finish dates. Those dates are calculated everytime the project is scheduled.
cProjects scheduling works taking a base date (either start project date or end project date) and afterwards it calculates the rest of the dates of the project. If you want to work with fixed dates it's necessary to use constraints (must start / must finish).
When importing from MSProject it is important to state clearly that scheduling is not the same than in cProjects, so it will never be a mirror replica, but a way to import the main data into your collaboration tool.
Hope this information is helpful.
Kind regards,
Neil
User | Count |
---|---|
10 | |
5 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.