on 07-08-2009 1:42 PM
Hello Experts
I am getting error " No standard cost estimate could be found for material "2000015" while posting the billing document to FI.
What can be the cause of the error?
Regards
Prashant.
Maintain a special procurement key in Costing 1 view of the material master and run CK11N
Review Transfer Control OKKM and special procurement types OMD9
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Prashant,
The material is cost relevant and for this your CO consultant has to create Standard Cost estimation. If this will create then error wont come.
Thanks,
Raja
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Check whether the standard cost is maintained in the ACCOUNTING view for the material or not ...
regards,
santosh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
100 | |
11 | |
11 | |
6 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.