Hi Alll experts,

i have one scenario where i am using the mile stone Billing plan and the start date decides all the other mile stone for the payment.

i want to put the Start date (FPLA-BEDAT) in the the incompletion procedure.

when i go in conig for defniing the incompletion procedure then this table is not there in the Incompletion Log.

how we can add this table and field for the incompletion

Please help

Thanks & Regards

Virandra Sharda

Accepted Solutions (0)

Answers (1)

Answers (1)

Jelena
Active Contributor
0 Kudos

FPLA table is not available in the incompletion procedure. You can make the field required by using a user exit. All SD user exits are listed here: