on 07-08-2009 7:16 AM
Dear All
I want to do workforce planning of my external contractors which is not the part of HR master data, I've only contract master data in MM module,
Can anyone tell me how I can attach/bring external/contractual manpower not in Internal HRmaster data to the project for workforce planning??
Is there any solution, please let me know.
Thanks
Atif
Hi,
There is no another option of bringing the contracts in workforce planning otherthan creating mini master in HR and maintian them as contractors.
You can see PA30 where the person the will be set as external or contractor.
Rgds
Sudhir reddy