cancel
Showing results for 
Search instead for 
Did you mean: 

PR remains open after TECO

Former Member
0 Kudos

Hi,

When I do TECO a deletion indiactor is set on all the open PR which are automatically generated by attaching the materials in the project builder.

However if i create account assigned PR thro' ME51N, then on doing TECO the deletion indicator does not get set for the PR.

The same is reflected in the reports ME5J / ME5A.

Is there any setting thro which the deletion indicator can be set on the open PR which are created manualy by thro ME51N once the TECO is done?

Thanks & Regards

Sanjay

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

As the PR is not generated throgh the PS functionality I dont think that deletion indicator would be set automatically for the manually created PRs.But as far as the Business Flow is concerned,system wont allow you to convert the PR into PO.As far as the report is concerned you can run a report for those WBS elements for whom status TECO has been set through the Status Profile concept.

Thanks and Regards

Shekhar

Former Member
0 Kudos

This message was moderated.