on 07-07-2009 12:28 PM
Missing data: Net value
Message no. VU019
Diagnosis
The system checked the document for completion and found some missing data.
System Response
You cannot continue processing.
Procedure
Enter the missing data.
Hi,
Its a standard system behaviour...
Once u create the scheduling agreement u have to define the schedule lines manually...like delivery date and order qty...
then only ur nat value field will be filled up with the value...
Try this
Reg
JJ