I am doing progress analysis by method- time proportionality for activity.
I have maintained a work package having the duration of 100 days ( for 5 months) . I have scheduled the project and run CNE1 and CNE5 and get the Planned POC as 22 % for the current period (4) fine. However if I am trying to run the progress analysis for next period (5), still I am getting the same planned POC as 22%. Why there is no change.
In my opinion the cumulative workdays should be 22+20 ( as per my calender) = 44, which is 44% of total days.
Also no copy of actual POC to activity on confirmation too.
Please advice where I am wrong
Regards
Zinni
Edited by: Makwana Zinni on Jul 7, 2009 12:36 PM
This message was moderated.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
102 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.