Budget Supplement

Former Member
0 Kudos

Dear All,

I have this typical problem in budget supplement

Now suppose the top WBS budget is 300/-, and first level budget is 200/-

and against the budget of 200/- I have posted actual(assigned) values of 150/-

Now i want to change the first level WBS budget to 150/-

I tried to subtract 50/- from both first level and top level WBS

but got error, saying the budget is exhausted.

Availability Control is active for the Projects.

Regards,

Vikas Sharma

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi,

Return the Budget of rs 50 from CJ35 from the WBS with Budget 200 only.

no goto CJ30 goto menu Edit>Select>Select all and Edit--> totalup.

Normaly when you total up the budget it will consider bottom up budgetting.

In normal scenario when ever you assgin the budget at top level as well as bottom level WBS, always try to supplement the budget to the top level. there are more chances of system using bottom up budgeting and the value at top level changes.

i hope you got the answer..!

Rgds

Sudhir reddy

Former Member
0 Kudos

Hi

Return the balance budget using CJ35

OR

Trnasfer the balance budget to another project using CJ34.

This is the way to post the balance budget.

Try this

Thanks

S.Murali