Order Plan Cost update on WBS Project

Former Member
0 Kudos

Dear Experts:

Is there any way to prevent Plan Cost from being updated in the assigned WBS Project? I have already tried removing the check marks from transaction OPSV (Order category 30)

In my current requirement, we are assigning Maintenance Orders to WBS Project therefore the all costs (Planned +Actual) show up on the WBS Project Budget report - which is the way it should work.

However I want to also prevent certain Order types from updating their costs in the WBS Project. However, I still want to assign them the WBS Element. Is there anyway to achieve this?

I have tried removing all check marks from transaction OPSV and reconstructed the Project Information database using report BPDIST00. Any thing else I can do?

Thanks in advance.

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

Beside removing assign fund in plan in OPSV, please try OPSC, be sure that planning in control indicator section is checked, then run CJEN.

Thanks

Former Member
0 Kudos

Thanks for your reply Hend.

OPSC is for Networks, I believe, which is Order category 20. I am working with Maintenance Orders, Order category 30.

Do you have other suggestions?

Thanks in advance