on 07-05-2009 3:12 PM
Hi, Guys, I got a problem in Sales order ATP check .
Given pick/pack date = 5 days in shipping point, In-house production date = 1 day in material master, request delivery date in item = July06, no UU stock, It;s supposed to hv confirmed delivery date = July 14 (as material aval.date = July 07 ).
Somehow, system always propose delivery date = July 15.
If in-house date removed, the ATP gives right date as July 13 .(request delivery date = July 06, and pick/pack date = 5 days.) so, where's the one more day come from ? Pls share your comments...
Have you checked load time, pick/pack time and any rounding of work days?
Also of your calendar and work days?
Are you using routes as this may have different times ?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hello, friend.
other points to consider:
1. route (transportation lead time)
2. purchasing lead times (if material is externally procured)
3. time of day when processing order (when you process late in the day, it might count an additional day)
regards.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
88 | |
7 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.