Hi All,

I need to increase BG work process from can on e tell me how to increaase and aslo after incrasing do i need to restart sap server and please tell me how to do.

Thanks in advance for the help,

Regards,

chandu

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

In RZ10, go to instance profile and increase the value of parameter

rdisp/wp_no_btc

once Ur done restart the instance.

Let us know if u have any issues,

Regards,

Ravi

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi,

First let me know how many work processes you have in your system .

Now need to have proper memory for setting these parameters .

To avoid performance problem set this parameter with in limits.

And the process told above is fine for setting this parameter.

Thanks

Rishi Abrol

Former Member
0 Kudos

Hi ,

how to restart the instance and i have to increase to 33 BG wpork process.How can i check if enough memory and other resources are avilable

Let me know thanks,

Regards,

raj

Former Member
0 Kudos

What,

U want to increase Background work process to 33.

Have u consulted any of Ur team member.

can we know, y u got this idea of increasing to 33BG wpork process

Let us know if u have any issues,

Regards,

Ravi

Former Member
0 Kudos

please ask your basis team to handle this issue

basically it is done from rz10 tcode in instance profile just fyi

Samrat