on 07-03-2009 7:01 AM
Dear Experts,
I have requirement like this my client receives P.O from customer price Rs/ 1 cr after recieving P.O they creats sales order with same price based on sales Order project will create automatically. as per project requirement Detailed Engineering dept creats BOM. while Drawing BOM itself if cost exceeded bove 1 cr they want recieve a message .
how can i achieve this please give me your valuable inputs
Regards
etr
close
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
please tell me what are the configuration steps required for that
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
You can budget the project in CJ30 for RS /1 CR and distubute to lower level WBSE 's as required.
Once if the budget exceeds the given value Rs 1 CR system will throw a error as BUDGET EXCEEDED.
For this in SPROPSCOSTSBUDGETDEFINE TOLERANCE LIMITS. Make this for 100% usuage with Activity 1.
Regards,
Nag.
Hi,
follow the path: IMG>PS>COSTS-->BUDGET:
1)maintain Budget Profile
inputs: Profile name, description, annual values check, past, future periods (ex 3,3), Acitivation type (1), Exchange rate type (M), controlling area currency check.
2) Assign budget profile to project definition
3) create number ranges
4) Define Tolerance limits
inputs: Controlling area, Budget profile, Tr.Grp (++), Act. (3), Usage (100).
Rgds
Sudhir Reddy
This message was moderated.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
85 | |
7 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.