Hello,
I have a requirement to implement the Import from MS Project Client.
The customizing is now implemented.
But the problem is if I import a MS Project Client file I have in cProjects a project definition which is ok. But then I have a "TASKHIERARCHY" as a phase and under this some tasks.
In MS Project I have a phase and some tasks under this phase.
How can i have a solution without this "TASKHIERARCHY"?
Hi
did you check the note: 958210 in that refer to PPT file
Rgds,
I hope this helps
Niranjan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
For mapping, you need to create Extra column say Text 21 in MSP where you should specify SAP Phase type key say 0001
now in SPRO mapping you need to specify that Text 21 belongs to phase type
similarly for task type create extra column where you wud enter relevent tsk type and select the same column in Mapping for task type.
Niranjan
Let me know if it helps !!!